Comú d’Ordino Launches €900K Phase to Double Water Network Between Ordino and Sornàs

Starting May 18, crews target the church-to-Sornàs roundabout section to fix cracks and losses from urban expansion. The effort tackles an outdated system amid growing demand, with future extensions to Llorts intakes.

Key Points

  • Project replaces old pipe with two lines: one to Coma de Suquer reservoir, one for local supply.
  • Part of €4.8M plan from 2025-2030 to modernize ageing 1980s infrastructure hit by leaks.
  • Work postponed near events like Trail 100 Andorra to limit disruption; traffic lights and parking cuts in place.
  • First phase from Coll d’Ordino to village entrance completed in 2025.

The Comú d’Ordino has launched the second phase of works to renew and duplicate the drinking water network between Ordino and Sornàs, with an investment exceeding €900,000.

The project began on Monday, 18 May, targeting the section from the roundabout in front of the church to the Sornàs roundabout. Crews will replace the existing pipe with two separate lines: one to carry water directly from mountain intakes to the Coma de Suquer reservoir, and the other to supply drinking water to buildings along the route.

This phase forms part of a broader modernisation plan for the parish’s hydraulic infrastructure, running progressively from 2025 to 2030 at an annual cost of around €800,000, for a total of nearly €4.8 million. The upgrades address an ageing network, mostly built in the 1980s, which has suffered increasing cracks, breaks and water losses due to urban growth and added connections. Future work will extend to Llorts, a key intake point for water from Sorteny, Rialb, Besalí and l’Angonella.

To limit disruption during peak visitor months and major events such as the Trail 100 Andorra by UTMB and the Nit de la Candela, officials postponed works on the stretch from the Ordino entrance roundabout to the church roundabout.

Traffic impacts include the temporary removal of five green-zone parking spaces and alternating passage controlled by traffic lights in the affected area.

The first phase, completed in 2025 between Coll d’Ordino and the village entrance roundabout, has already finished.